Key | Value |
cables | 3 |
circuits | 1 |
description | Relocated San Simon-Pulilan of Hermosa-San Simon-Duhat-Balintawak, only 4 towers under TransCo plan and alignment (255, 256, 266, 267) were used while ROWs or portions and lands of the 58 poles (228-254, 257-265, 268-289) are NGCP-acquired and designated. |
frequency | 60 |
operator | National Grid Corporation of the Philippines |
operator:short | NGCP |
operator:type | private |
operator:wikidata | Q28197109 |
operator:wikipedia | en:National Grid Corporation of the Philippines |
owner | National Grid Corporation of the Philippines |
owner:short | NGCP |
ownership | private |
power | line |
spacers_broken | uncalculated |
start_date:NGCP | 2011-03-25 |
start_date:TransCo | 2009-01-15 |
tower_to_tower_distance | 400-700m |
voltage | 230000 |
year_of_construction:NGCP | 2009-11..2011-03-25 |