OSM Way 1184179589: Hermosa-San Simon-Duhat-Balintawak (relocated San Simon-Pulilan)

ID:

KeyValue
cables3
circuits1
descriptionRelocated San Simon-Pulilan of Hermosa-San Simon-Duhat-Balintawak, only 4 towers under TransCo plan and alignment (255, 256, 266, 267) were used while ROWs or portions and lands of the 58 poles (228-254, 257-265, 268-289) are NGCP-acquired and designated.
frequency60
operatorNational Grid Corporation of the Philippines
operator:shortNGCP
operator:typeprivate
operator:wikidataQ28197109
operator:wikipediaen:National Grid Corporation of the Philippines
ownerNational Grid Corporation of the Philippines
owner:shortNGCP
ownershipprivate
powerline
spacers_brokenuncalculated
start_date:NGCP2011-03-25
start_date:TransCo2009-01-15
tower_to_tower_distance400-700m
voltage230000
year_of_construction:NGCP2009-11..2011-03-25
year_of_construction:TransCo2008-02-18..2009-01-15